2015 Summer Construction/Maintenance Projects

2015 Summer Construction/Maintenance Projects 

Several construction/maintenance projects on campus will begin at the end of May and continue through the summer. We ask members of the campus community to use caution around equipment and contractors working in these areas. All project start and completion dates, weather permitting, are listed below. Facilities Services will send updates throughout the summer.

​  ​              PepsiCo Roof Replacement: June 1- July 31
                 ​  ​Heavy equipment and a crane will be parked near the building and in the parking lot.

                ​​The Gerber Center Library Roof Replacement: May 26-August 20
                  The ADA entrance on the east side of the building will be closed during this project.

                 The Gerber Center Library Quad Entrance Stair Replacement: June 1-August 20
                  Half of the staircase will be accessible during construction.  

                Westerlin Hall Remodel: May 26-August 20
                  The Jenny Lind Wing, including all three floors, will be closed.               

                Centennial Roof Replacement: Date to be determined
Sections of the parking lot (Lot E) may be closed at times for contractor equipment.

                Knowlton Complex - Ericson Stadium Locker Rooms and Restrooms Tuck-Pointing: Date to be determined
The locker rooms and restrooms will be closed during this project.

                Founders Hall Tuck-Pointing: May 26-August 20
Access to some entrances may be restricted during this project.

                Andreen Hall Tuck-Pointing: June 1-August 20
Access to some entrances may be restricted during this project.

                Lower Quad Chilled Water/Steam Line Replacement: June 1 -August 20
                  The lower quad will still be accessible during construction.

                The Gerber Center Library Quad Entrance Door Replacement: June 29 - July 3rd
                    ​T​​here will be limited access to these entrance doors during construction.

                7th Avenue Retaining Wall Replacement: Date to be determined
                   This is the retaining wall that runs in front of Old Main. The sidewalk will be closed during this construction.   

              ​  Carver Tennis Courts Chilled Water/Steam Line Replacement: Date to be determined
The pipes between the Carver tennis courts and the Heating Plant will be replaced. The Carlsson Evald Hall parking lot (Lot U) will be     closed during this project.

Any questions or concerns can be directed to Joe Scifo - ​ ​or David Baker -

Thank you in advance for your patience while we complete these projects.